CPI vs SPI: Analysing Project Progress with Proteus Project Software

Xergy Group
Dashboards & Reporting Digital Transformation project management Resource Management
CPI vs SPI - Proteus Project Software

With decades of experience working on energy sector projects, the Proteus team is more than aware of the challenges that come with managing complex initiatives. We have found that our clients rely on accessing accurate project data to ensure project success. This allows our clients to closely monitor progress and performance. Two vital metrics that can significantly aid in this endeavour are the Cost Performance Index (CPI) and the Schedule Performance Index (SPI). In this blog, we will explore CPI vs SPI, we will delve into the importance of these metrics, their calculation methods, their interpretation, and their application in real-world scenarios. Additionally, we’ll explore how project management software like Proteus can empower project managers in optimising CPI and SPI.

Summary

This article explains the Cost Performance Index (CPI = EV/AC) and Schedule Performance Index (SPI = EV/PV) as essential earned value metrics for monitoring cost and time efficiency. It clarifies how to interpret values (greater than 1 is favourable) and provides worked examples. The piece outlines why tracking CPI and SPI improves budget control, schedule management, risk mitigation, forecasting, and stakeholder communication. It also shows how Proteus software automates EVM calculations and dashboards to surface variances early, optimise resources, and enhance delivery across the project lifecycle.

Cost Performance Index (CPI):

CPI is a critical metric used to evaluate a project’s cost efficiency. It measures the ratio between the Earned Value (EV) and the Actual Cost (AC) of the work performed. The Earned Value represents the value of the work completed as per the project schedule, while the Actual Cost indicates the actual expenditure incurred. The formula for calculating CPI is as follows:

CPI = EV / AC

    Cost Performance Index (CPI) Example:

    Let’s say a wind turbine development project has an Earned Value (EV) of £2,000,000 and an Actual Cost (AC) of £2,200,000. Using the CPI formula:

    CPI = £2,000,000 / £2,200,000 ≈ 0.91

      Interpretation: The CPI of 0.91 indicates that the project is over budget, as the cost performance is less than 1.

      Schedule Performance Index (SPI):

      SPI, on the other hand, assesses the project’s time efficiency. It measures the ratio between the Earned Value (EV) and the Planned Value (PV). The Planned Value represents the value of the work that was scheduled to be completed at a given point in time. The formula for calculating SPI is as follows:

      SPI = EV / PV

        • CPI > 1: Indicates that the project is under budget, which is desirable.
        • CPI = 1: Suggests that the project is on budget, as the earned value matches the actual cost.
        • CPI < 1: Implies that the project is over budget, indicating potential cost overruns.
        • SPI > 1: Shows that the project is ahead of schedule, which is favourable.
        • SPI = 1: Indicates that the project is progressing as per the planned schedule.
        • SPI < 1: Suggests that the project is behind schedule, and corrective actions may be needed to catch up.

        Schedule Performance Index (SPI) Example:

        Consider the same wind turbine project with an Earned Value (EV) of £1,800,000 and a Planned Value (PV) of £2,000,000. Calculating the SPI:

        SPI = £1,800,000 / £2,000,000 = 0.9

          Interpretation: The SPI of 0.9 suggests that the project is behind schedule, as the schedule performance is less than 1.

          Why it is Important for Project Managers to Monitor CPI and SPI

          Monitoring the Cost Performance Index (CPI) and Schedule Performance Index (SPI) is crucial for several reasons, as they provide valuable insights into the overall health and progress of a project. There are multiple reasons why it is important for project managers to monitor CPI and SPI:

          1. Project Health Assessment: CPI and SPI offer a comprehensive assessment of a project’s performance in terms of cost and schedule adherence. By comparing planned values to actual values, project managers can identify if the project is on track or if there are any deviations. This assessment helps in early issue detection and enables timely corrective actions.
          2. Budget Control: CPI is directly related to cost efficiency. It indicates whether the project is over or under budget based on the value of work completed. Monitoring CPI allows project managers to control costs, avoid overruns, and make informed decisions about resource allocation and budget adjustments.
          3. Time Management: SPI measures schedule performance by comparing the work completed with the planned schedule. This helps in understanding if the project is running ahead or behind schedule. By keeping track of SPI, project managers can take proactive measures to manage deadlines, prevent delays, and maintain project momentum.
          4. Risk Management: Deviations in CPI and SPI may indicate potential risks and challenges within the project. Continuous monitoring helps project managers identify areas that need attention and devise risk mitigation strategies before issues escalate.
          5. Stakeholder Communication: CPI and SPI provide quantifiable metrics that are easily communicable to stakeholders, clients, and team members. These metrics offer a clear picture of the project’s progress, fostering transparency and building confidence in the project’s success.
          6. Decision Making: The data provided by CPI and SPI empowers project managers to make informed decisions. For instance, if CPI indicates a project is over budget, managers can prioritise cost-saving measures or reevaluate scope. Similarly, SPI insights can prompt managers to adjust resources or schedule to meet deadlines.
          7. Performance Improvement: CPI and SPI are not only indicators of current project status but also useful benchmarks for improvement. Project managers can set targets for future CPI and SPI values based on historical data, aiming to enhance project efficiency over time.
          8. Project Completion Forecasting: By analysing CPI and SPI trends, project managers can forecast the project’s likely completion date and total cost. This enables better resource planning and setting realistic expectations for stakeholders.
          9. Continuous Improvement: Tracking CPI and SPI encourages a culture of continuous improvement within the project team. Regular performance evaluation and goal-setting help in optimising processes and practices for better future outcomes.
          10. Compliance and Reporting: For certain projects, organisations, or industries, there may be contractual or regulatory requirements to monitor and report CPI and SPI. Adhering to these guidelines ensures compliance and accountability.

          What Software Manages CPI and SPI?

          Project management software tools play a crucial role in assisting project managers in monitoring CPI and SPI effectively. Software like Proteus offers features such as Project Controls modules for Earned Value Management (EVM) that automatically calculate CPI and SPI based on the project’s data. Project managers can input data on completed tasks and costs, enabling real-time monitoring of the project’s progress against the planned schedule and budget. By regularly assessing CPI and SPI values in an easy-to-use interface, project managers can identify potential budget and schedule deviations early on, allowing them to take corrective actions promptly.

          Project management tools help optimise resource allocation by identifying areas where resources may be underutilised or overburdened, contributing to improved project efficiency.

          In conclusion, the Cost Performance Index (CPI) and Schedule Performance Index (SPI) are invaluable metrics for assessing a project’s progress. CPI indicates cost efficiency, while SPI measures time efficiency. Both metrics are calculated using specific formulas and can be interpreted to gain insights into the project’s status. These metrics provide critical data points that help in assessing project health, controlling budgets, managing schedules, and making informed decisions for successful project delivery. Continuous monitoring of CPI and SPI fosters a proactive and improvement-oriented approach, leading to increased project efficiency and overall success. Project management tools equipped with Earned Value Management modules can facilitate continuous monitoring and enable project managers to proactively address deviations. By leveraging CPI and SPI, engineers can ensure the successful delivery, for example, of sustainable wind turbine projects, contributing to a greener future for generations to come.

          What is Proteus?

          Proteus developed by a Scottish-based tech company, Xergy Group, is an end-to-end project management solution developed for the energy and engineering consulting industries.

          Proteus is industry-proven and enables consultancies to meet project demands across the full lifecycle, from proposal development to project delivery. With robust sales and project delivery modules, Proteus helps its customers win more business, increase efficiencies, manage expenditures, and improve project controls.

          Critical workflows, automation, and controls are integrated into Proteus. These include opportunity evaluation, proposal building, resource planning, budget tracking and forecasting, real-time multi-level restricted dashboards, and project performance analytics.

          Third-party integrations and customised solutions allow Proteus’ users, which include C-suite, project leads, and engineers, to get the exact software solution needed for their business.

          We offer a free onboarding consultation service to ensure your company account is set up to your company’s needs.

          Proteus operates under a software-as-a-service (SaaS) model. We offer Enterprise packages and flexible pricing solutions: contact our team to learn more.

          Q&A

          Question: What are CPI and SPI, and how do I calculate them? 

          Short answer: They are earned value metrics that show cost and schedule efficiency. Cost Performance Index (CPI) = Earned Value (EV) / Actual Cost (AC). Schedule Performance Index (SPI) = Earned Value (EV) / Planned Value (PV). EV is the value of work completed, AC is what you actually spent, and PV is what you planned to complete by a given date.

          Question: How do I interpret CPI and SPI values? 

          Short answer: For both metrics, 1.0 is on target. Greater than 1.0 is favourable; less than 1.0 is unfavourable. Specifically: CPI > 1 means under budget; CPI = 1 on budget; CPI < 1 over budget. SPI > 1 means ahead of schedule; SPI = 1 on schedule; SPI < 1 behind schedule and may require corrective action.

          Question: Can you show a quick example of CPI and SPI in practice? 

          Short answer: In a wind turbine project: with EV = £2,000,000 and AC = £2,200,000, CPI = 2,000,000 / 2,200,000 ≈ 0.91, indicating the project is over budget. For schedule, with EV = £1,800,000 and PV = £2,000,000, SPI = 1,800,000 / 2,000,000 = 0.9, showing the project is behind schedule.

          Question: Why should project managers monitor CPI and SPI throughout a project? 

          Short answer: They provide an early, quantifiable view of project health for cost and schedule. Tracking them supports budget control, deadline management, risk identification and mitigation, informed decision-making, clear stakeholder communication, performance benchmarking and continuous improvement, forecasting of final cost and completion date, and compliance/reporting where required.

          Question: How does Proteus help manage and improve CPI and SPI, and what does getting started involve? 

          Short answer: Proteus includes Project Controls and Earned Value Management features that automatically calculate CPI and SPI from project data, surface variances on real-time, role-based dashboards, and help optimise resources to correct cost and schedule drift. It’s an end-to-end SaaS solution with sales and delivery modules, third-party integrations, and customizable setups for teams from C‑suite to engineers. You can get started without an IT team and access a free onboarding consultation and support from product experts. Enterprise packages and flexible pricing are available by contacting the Proteus team.

          We designed Proteus to be simple, and that means you can get up and running on Proteus without an IT team or support from a programmer. You will want to spend a bit of time configuring the admin console so that you have everything set up to suit your company structure, but it’s very intuitive and you don’t need a PhD in IT.

          However, we want you to get the best out of what is a brilliantly powerful tool, so don’t hesitate to ask for our support. We have a team of product experts who are ready to help you with the configuration process, so get in touch today by filling out the form below:


          Schedule a free Proteus demo